In May 2019, VELCO installed a temporary substation in order to begin upgrades to the existing Barre substation. Construction began early summer with yard excavation, concrete work and conduit installation underway. VELCO expects the new control building to be complete by September 2019 and the upgraded substation to be commissioned by the end of the year.