Barre Substation construction update, 7/18/2019

In May 2019, VELCO installed a temporary substation in order to begin upgrades to the existing Barre substation. Construction began early summer with yard excavation, concrete work and conduit installation underway. VELCO expects the new control building to be complete by September 2019 and the upgraded substation to be commissioned… Read More »

VELCO to host informational meeting on proposed Barre area upgrades

Barre, VT¬†– 6 October 2017:¬†Vermont Electric Power Company (VELCO) is inviting neighbors in the Barre area, and other interested people, to an informational session about a proposed project to upgrade the Barre substation. The meeting will be held Wednesday evening, October 11, 2017, from 6:00 p.m. to 7:00 p.m., at… Read More »