Notice: Undefined index: HTTP_COOKIE in /home/velco/website/public_html/news/wp-content/themes/velco/functions.php on line 43
Bennington Substation Upgrade Project

Category: Bennington Substation Upgrade Project

Keys to a Successful Project

Upon completion, many details that made the project successful become hidden. Behind the scenes it’s a team effort from planning, right-of-way, engineering, procurement, construction, accounting, and others for each load of rock placed under the roadway or each control wire connected to a switch inside a building. Keys to success:… Read More »

Construction Updates

Like all projects, this one faced some challenges during construction: 3-4 month delay on start of construction due to a longer than anticipated permitting process. Started fall of 2012. Added complexity to site grading and foundation installation due to winter construction. Above average rainfall in the spring of 2013, which… Read More »