Bennington Substation Upgrade Project

COVID-19 Update: Protecting the health and safety of our employees, customers, owners and our communities is - and always has been - VELCO's number one priority. Our focus remains on safety and reliability during this unprecedented time. VELCO has implemented our remote work policy in an effort to reduce the spread of COVID-19. During this transition, VELCO's offices will not be open to visitors. If you have questions or need to contact a VELCO representative, please call 802-770-6221 or use our Contact Us form. Click here for more information.

Category: Bennington Substation Upgrade Project

Keys to a Successful Project

Upon completion, many details that made the project successful become hidden. Behind the scenes it’s a team effort from planning, right-of-way, engineering, procurement, construction, accounting, and others for each load of rock placed under the roadway or each control wire connected to a switch inside a building. Keys to success:… Read More »

Construction Updates

Like all projects, this one faced some challenges during construction: 3-4 month delay on start of construction due to a longer than anticipated permitting process. Started fall of 2012. Added complexity to site grading and foundation installation due to winter construction. Above average rainfall in the spring of 2013, which… Read More »