Remaining work in VT during outage: adjusting oil pressure on a voltage transformer, pin disconnect switch, test switch and bus, and relay testing.

Remaining work in NY during outage: test switch and bus, relay testing, install one transmission structure and string lines over the road.

Planning for completion of work and sign-offs by 12-27-17, final site walk-downs on 12-28-17, and begin energization sequence on 12-28-17 or 12-29-17 to restore service.