Remaining work in VT during outage: Verification of contractor testing results and relay testing.

Remaining work in NY during outage: String transmission lines over the road and make connections.

Planning for completion of work and sign-offs by the end of day 12-28-17, final site walk-downs on 12-29-17, and begin energization sequence on 12-29-17 to restore service.

Due to the extreme cold weather, another conference call is scheduled for 2 PM tomorrow (12-28-17) which will be followed by another update posting to confirm the energizing date.