Remaining work in VT during outage: Final inspection prior to energization.

Remaining work in NY during outage: String transmission lines over the road and make connections.

Planning for completion of work by the end of day 12-29-17, final site walk-down on 12-30-17, and begin energization sequence on 12-30-17 to restore service.

Due to the extreme cold weather and equipment problems, another conference call is scheduled for 12PM on 12-29-17 which will be followed by another update posting to confirm the energizing date.