Remaining work in VT during outage: Final inspection prior to energization.

Remaining work in NY during outage: Stringing shield wire over the road and making connections.

Expecting completion of work by the end of day 12-29-17, final site walk-down on 12-30-17, and begin energization sequence on 12-30-17 to restore service.