Vermont Electric Power Company
Login|Projects|Careers
  • Home
  • About
    • Mission, Vision & Values
    • Leadership
    • History
    • Awards & Partnerships
    • Charitable Giving
    • Media Center
    • Learning Center
    • News
    • Regulatory
    • System Map
  • Our Work
    • Projects
    • Land Management
    • Environment
    • Planning
    • Safety
    • Innovation
  • Our Services
    • Vermont Transco
    • Interconnection
    • Rates, Tariffs, Business Practices
    • Regulatory Requirements
    • Operating Committee
    • VT System Planning Committee
    • Load Information
    • Weather Center
    • Weather Forecast
  • Contact
    • In Case of Emergency
    • Key Contacts
    • Careers
    • Contractors & Vendors
    • Directions

Our Work

  • Projects
    • Florence
    • FC Line Upgrade
    • Irasburg
    • New Haven
    • North Rutland
    • Past Projects
  • Land Management
    • Real Estate
    • Trees & Vegetation
    • Topics & Resources
    • Contact Land Management
  • Environment
    • Environmental Policy
  • Planning
    • Long-Range Plan
  • Safety
    • Hunting Safety
    • Farm Safety
    • Logging Safety
    • First Responder
  • Innovation
    • VT Weather Analytics Center
  • Home

PV20 Submarine Cable Replacement Project

  • About
  • Regulatory Process
  • Get Involved
  • Updates

Updates

Before project permitting, during the permitting phase and during construction, we use this update section to provide news and information about VELCO projects in process. These regular updates ensure that the public can follow and have input into our projects. 

PV20 Outage Update (12-29-17)

Posted on 12/29/2017

Remaining work in VT during outage: Final inspection prior to energization. Remaining work in NY during outage: Stringing shield wire over the road and making connections. Expecting completion of work by the end of day 12-29-17, final site walk-down on 12-30-17, and begin energization sequence on 12-30-17 to restore service. Read more »

PV20 Outage Update (12-28-17)

Posted on 12/28/2017

Remaining work in VT during outage: Final inspection prior to energization. Remaining work in NY during outage: String transmission lines over the road and make connections. Planning for completion of work by the end of day 12-29-17, final site walk-down on 12-30-17, and begin energization sequence on 12-30-17 to restore service. D... Read more »

PV20 Outage Update (12-27-17)

Posted on 12/27/2017

Remaining work in VT during outage: Verification of contractor testing results and relay testing. Remaining work in NY during outage: String transmission lines over the road and make connections. Planning for completion of work and sign-offs by the end of day 12-28-17, final site walk-downs on 12-29-17, and begin energization sequence on 12-2... Read more »

View all news updates for the PV20 Submarine Cable Replacement Project.

PV20 Project

Date/Time Title Details
05/20/2015 5:30pm
through
05/20/2015
Grand Isle Public Meeting View Details
Vermont Electric Power Company
  • Home
  • About
    • Mission, Vision & Values
    • Leadership
    • History
    • Awards & Partnerships
    • Charitable Giving
    • Media Center
    • Learning Center
    • News
    • Regulatory
    • System Map
  • Our Work
    • Projects
    • Land Management
    • Environment
    • Planning
    • Safety
    • Innovation
  • Our Services
    • Vermont Transco
    • Interconnection
    • Rates, Tariffs, Business Practices
    • Regulatory Requirements
    • Operating Committee
    • VT System Planning Committee
    • Load Information
    • Weather Center
    • Weather Forecast
  • Contact
    • In Case of Emergency
    • Key Contacts
    • Careers
    • Contractors & Vendors
    • Directions

Terms of Use | Site Map

© 2013 - 2022 VELCO, 366 Pinnacle Ridge Rd, Rutland, VT