Notice: Undefined index: HTTP_COOKIE in /home/velco/website/public_html/news/wp-content/themes/velco/functions.php on line 43

News

VELCO Open raises record funds for Rutland skate park

Rutland, VT – (October 5, 2018): The 2018 VELCO charity golf tournament raised more than $19,000 in its 23rd edition on September 7. The proceeds, which topped all previous tourneys by a wide margin, will be donated to benefit the Flip Side Skate Park Program at the Rutland Recreation Center. Read More »

Vermont Electric Power Company Alerts Vermont Residents to Phone Scam

Rutland, VT – (April 20, 2018): Vermont Electric Power Company (VELCO) is alerting Vermont residents to a telephone scam involving callers claiming to be representing VELCO. The scammers have targeted Vermont businesses demanding credit card information to pay an account balance or face disconnection. VELCO has no residential or commercial business… Read More »

PV20 Outage Update (12-29-17)

Remaining work in VT during outage: Final inspection prior to energization. Remaining work in NY during outage: Stringing shield wire over the road and making connections. Expecting completion of work by the end of day 12-29-17, final site walk-down on 12-30-17, and begin energization sequence on 12-30-17 to restore service. Read More »

PV20 Outage Update (12-28-17)

Remaining work in VT during outage: Final inspection prior to energization. Remaining work in NY during outage: String transmission lines over the road and make connections. Planning for completion of work by the end of day 12-29-17, final site walk-down on 12-30-17, and begin energization sequence on 12-30-17 to restore… Read More »

PV20 Outage Update (12-27-17)

Remaining work in VT during outage: Verification of contractor testing results and relay testing. Remaining work in NY during outage: String transmission lines over the road and make connections. Planning for completion of work and sign-offs by the end of day 12-28-17, final site walk-downs on 12-29-17, and begin energization… Read More »

PV20 Outage Update (12-26-17)

** No change in project status** Remaining work in VT during outage: adjusting oil pressure on a voltage transformer, pin disconnect switch, test switch and bus, and relay testing. Remaining work in NY during outage: test switch and bus, relay testing, install one transmission structure and string lines over the… Read More »

PV20 Outage Update (12-21-2017)

Remaining work in VT during outage: adjusting oil pressure on a voltage transformer, pin disconnect switch, test switch and bus, and relay testing. Remaining work in NY during outage: test switch and bus, relay testing, install one transmission structure and string lines over the road. Planning for completion of work… Read More »